Key Takeaways

  • The US Navy expects to hit full-rate construction of the Columbia-class submarine in 2031.
  • The first Columbia-class submarine is expected for delivery in 2028.
  • The District of Columbia is about 65-66% complete and on track for delivery in 2028.
  • The second Columbia-class submarine, Wisconsin, is roughly 35% complete and still tracking for an on-schedule delivery in 2030.

Strategic Implications

This acceleration may indicate the Navy’s efforts to address delays and workforce challenges. The focus on delivering modules by the end of 2025 suggests a prioritization of program recovery. However, the exact timeline remains uncertain, and the Navy must navigate supply chain complexities.